4.0 Final System
4.1 Final Design of CSP Rig & Cost
The constructed rig serves as a prototype for testing. The objective is to develop a scalable, commercially viable CSP system that is efficient, durable, and easy to transport and assemble for hot water applications in Tanjung Balai, with potential deployment in other suitable regions. Multiple designs are evaluated for the light subsystem and rig (supporting structure), while the thermal transmission and energy storage systems remain consistent throughout.
Design 01
The rig is constructed from commercially available PVC pipes and joints, making it cost-effective, durable, and easy to transport and assemble, while remaining strong enough to support the reflectors (polished stainless-steel) and receiver (copper).
The design uses only a parabolic dish configuration to maximise light reflection and avoid focal point conflicts from multiple configurations. However, it may not be practical due to high manufacturing costs, as it requires conical rolling (more expensive than standard sheet metal bending) and may lead to material wastage due to its triangular geometry.
The total reflective surface area: 0.9 m².
Design 02
The reflectors follow a configuration similar to that of the developed test rig. However, their dimensions have been modified to maximise reflective area while avoiding conflicts between focal points.
The curved rectangular metal sheet reflectors are similar to those used in the test rig and can be easily fabricated through standard bending processes. Additionally, the parabolic dish can be manufactured using techniques similar to those used in wok fabrication, making it practical and cost-effective.
The total reflective surface area: 2 m²
Given that the application involves combining multiple rigs, the total system cost is assessed.
Design 03
Although Design 02 maximises reflective surface area, its high cost when you combine multiple rigs together, results in a longer payback period, making it less justifiable from the client’s perspective. Therefore, Design 03 is proposed as a more cost-effective and scalable CSP solution.
In this design, a thin stainless steel sheet is pressed into a parabolic dish using a process similar to sink fabrication. By combining the reflector and structural functions into a single component, costs are reduced by 37% through the elimination of multiple supporting parts.
The total reflective surface area: 0.956 m²
4.2 Optimum parameters for system
The island layout for each island size is shown below, designed to minimise pipe length while allowing modular expansion.
As the system connects to the water mains, existing components must be modified. For transmission, 304 stainless steel pipe will be used for durability, high temperature resistance, and compatibility with water mains [11][12]. The pipe sizes are compared, between:
- 1/8" nominal pipe, smallest common size [13]
- 3/4" nominal pipe, commonly used in residential plumbing [14]
- 1" nominal pipe, commonly used in residential plumbing [14]
Furthermore, two configurations to connect the receivers to the TES are considered:
- Parallel (each receiver connected independently to the TES)
- Series (receiver connected sequentially)
Finally, the optimal island size for the island has to be determined.
Detailed derivations, calculation methodology, and supporting models are provided in Appendix A.
The following assumptions are applied in the calculations within this section:
- 5ºC temperature difference across TES inlet and outlet, within typical ranges of water thermal systems, [15][16] to balance residence time within TES and heat transfer effectiveness
- no heat loss through pipe for flow rate calculation, allowing immediate usage of heat energy calculation (Q = mc∆T)
- turbulent flow in pipes for system head
- heat loss through pipes only
- 60ºC water and 25ºC ambient temperature for high temperature difference analysis
Pipe size
For optimal pipe size, the system head is compared across different pipe diameters (see Appendix A). A higher system head indicates greater flow resistance, which requires a more powerful pump.
3/4” and 1” pipes provide similar low system head, with minimal differences among the 3 sizes across both configurations. 3/4” pipe is selected for providing comparable hydraulic performance with less material requirements.
Parallel vs series configuration
The thermal efficiency of the piping network is evaluated using the commonly available 25mm thickness aircon insulation that exhibits heat loss of 7.1722W/m, satisfying design requirements of ≤7.95W/m. (see Appendix A) [8]
Aircon insulation is used due to its flexibility and ease of installation, which eliminates the installation issues observed from PUR/PIR insulation from the integreated test. It is also readily available and has good thermal properties similar to PUR/PIR under shaded conditions seen in the insulation tests.
The results shows that thermal efficiency decreases with island size in the parallel configuration but increases in the series configuration. This is due to the average pipe length per rig decreasing in the series configuration, but increasing in the parallel configuration. Therefore, the series configuration is chosen for lower heat loss.
Optimal island size
Design 1: Maximum islands
Design 1 focusses on maximising total useful energy collected and the maximum number of islands that fits on one roof is assessed for all island size. The total pipe length is estimated based on the system layout geometry and used in the calculations in this section, with detailed calculations provided in Appendix A.
The pipe loss in the entire system indicates island size of ≥3 meets design requirements of 17.5%. (see Appendix A)
The total useful energy is compared since not all configuration uses all the available space. The total useful energy peaks at system sizes 4 and 6, with island size 6 producing 730.5W less than island size 4 (a 0.9016% reduction). Both configurations have a compact rectangular/square layout that supports modularity and efficient space utilisation. A cost analysis is used to finalise the optimal size.
Cost analysis
The equipment required for each island follows the diagram below (see Appendix A for details).
Using bulk purchasing assumptions, the cost of a single island and the total system for the thermal transmission subsystem is evaluated.
Per rig, island size 6 is cheaper by SGD $14.51 (31.64%), and for the entire system (two roofs), it is cheaper by SGD $19,582.14 (32.70%). Overall, island size 6 offers lower cost while only incurring a minimal reduction in energy output, making it the more economical option. However, despite this reduction, the overall system cost remains high, resulting in a longer payback period.
Design 2: Meeting requirements
In design 2, the focus is on meeting the maximum daily hot water requirements of the hotel (7500L). This minimises the energy wastage caused by excessive hot water production (up to 12,880L in design 1) and reduces the overall implementation costs. The total pipe length is estimated based on the system layout geometry and used in the calculations in this section, with detailed calculations provided in Appendix A.
The pipe losses in this design indicates island size ≥3 meets design specifications.
Considering the thermal efficiency of the entire system (used to maximise the stored energy), the efficiency peaks at island size 9 with local peak at 6. This corresponds to the trends seen in the total useful energy.
Cost analysis
The 2 island sizes are compared by cost analysis.
Per rig, island size 6 is cheaper by SGD$14.32 (31.34%) and overall 2 roof system for island size 6 is cheaper by SGD$10,767.88 (30.81%). The difference is largely due to the pumps, as the island size of 9 requires more expensive pumps to overcome the higher system head requirements. Overall, the island size 6 is best using the design focussed on meeting hotel requirements, making the cost of the thermal transmission section SGD$24,180.80.
Overall, the final thermal transmission system has a heat loss of 7.1722W/m, pipe loss of 11.6511% and power consumption of 10W per rig, [13] satisfying the design specifications.
The entire system thus requires input of 7560W to power the pumps, which adds a cost of SGD$340.20 to the calculations above, making the total cost of the entire system SGD$24,521. [25]
4.4 Overall Cost Analysis
The final proposed design consists of islands as seen below.
The total cost of the entire system is:
For the hotel in indonesia, with electricity costs of Rp1444,70/kWh, [26] or SGD0.11 (as of 6 April 2026), the electricity costs is expected to be SGD5,249.61 per year. (see Appendix C for calculations). Thus, the payback period is 24.30 years. This indicates that under current costs and electricity prices, the system may not be economically attractive without further improvements in efficiency, reduction of initial costs or increase in electricity prices.
However, for businesses, the incentives of adopting renewable energy goes beyond saving electricity costs. The Indonesian government is actively encouraging industries, including tourism industry, to adopt sustainable energy and reduce their reliance on non-renewable resources. [27][28][29] For hotels, adoption of renewable energy drives them to the direction of attaining green building or green hotel standards, making them eligible for incentives or awards. [30][31] Overall, beyond monetary benefits, they seek to gain government support and even more customers from their status.
Appendix A: System design detailed process with all results
The main MATLAB script is system_scaling_single.m for series configuration and system_scaling_separate.m for parallel configuration.
Key assumptions
- Temperature difference across TES = 5°C
- Heat loss in pipes neglected for flow rate calculations
- Flow is assumed turbulent
- Heat losses occur only through piping network
- Ambient temperature = 25°C, water temperature = 60°C for heat loss analysis
Pipe size
The mass flow rate is determined using an energy balance across the TES, , where a temperature difference of 5°C is used. The corresponding mass flow rate and volumetric flow rate are calculated. All flow rates presented in this report refer to volumetric flow rate.
For the parallel configuration, the flow rate is constant at 0.409 L/min for all island sizes. For the series configuration, the flow rate varies with island size and is determined using the same energy balance. The results are shown below.
System head is given by: System head = Static head + Hydraulic losses
For a closed loop system, the static head is 0m.
Hydraulic losses are the sum of pipe losses and minor losses. Pipe losses are calculated using the Darcy–Weisbach equation:
Minor losses are calculated using loss coefficients (K-values) for each fitting:
A constant friction factor (f) of 0.02 is assumed, corresponding to turbulent flow. The rig layout to obtain internal pipe length (within island) and fittings required are below.
The system head is computed using a MATLAB function (NPSH_system_head_single.m for series configuration and NPSH_system_head_separate.m for parallel configuration). The resulting system head for each pipe size is shown below.
For the parallel system
For the series system
Thermal efficiency of pipes in island
The thermal efficiency is defined as:
Heat loss is calculated using a rate of 7.1722 W/m, obtained from the following assumptions:
- 25mm thickness of aircon insulation
- 3/4" pipe
- 35ºC temperature difference between water and atmosphere
The heat loss per meter is derived from conduction (through pipe and insulation) and convection (within the pipe and to atmosphere):
: Heat loss per unit length (W/m)
: Length of the pipe (m)
: Water temperature (°C)
: Ambient temperature (°C)
: Inner radius of the pipe (m)
: Outer radius of the pipe/Inner boundary of insulation (m)
: Outer radius of the insulation (m)
: Convective heat transfer coefficient of water (W/m²·K) – Inside pipe
: Convective heat transfer coefficient of air (W/m²·K) – Outside insulation
: Thermal conductivity of the pipe (W/m·K)
: Thermal conductivity of the insulation (W/m·K)
Using the pipe length estimation from layout above, the thermal efficiency of the pipes in a system of rigs is obtained for the series and parallel configuration. Thermal efficiency is computed uisng a MATLAB function (pipe_efficiency_single.m for series configuration and pipe_efficiency_separate.m for parallel configuration.)
The resulting thermal efficiency is shown below:
Optimal island size: Design 1
The island size is evaluated based on the following analysis. The layout of the islands on one of the rooftop is obtained (see Appendix B), using the sample connection plans below.
The length of pipe between the islands and to the hot water storage tank (total external pipe length) are inserted into the MATLAB script overall_sys_eff.m and is calculated with referenced to the sketches in Appendix B.
The total external pipe length and the sum of all the internal pipe length (within each island) are used to evaluate system performance, including thermal efficiency and pipe loss.
The thermal efficiency of the entire piping system on one rooftop is obtained (see below).
Pipe loss (expressed as a percentage of energy loss relative to output energy) is defined as:
Using this equation, the results are shown below.
Cost analysis: Design 1
The cost of the system are compared considering the layout provided in the figures. The additional fittings required along with the pipes are:
- Tank connectors, to connect the pipes to the TES tank
- Couplers, to connect the pipes to the pump and to join pipe to the receiver
- Pressure relief valve, for safety against high pressure
- Non-return valve, to prevent backflow
Using cost of purchasing in bulk we get the costs below.
Optimal island size: Design 2
In design 2, we limit the number of rigs to meet the requirements of the hotel. Of the total 7500 L required, 3750 L is allocated to each roof to ensure equal distribution of hot water production. The minimum number of rigs required per roof is 370, with each rig contributing approximately 10 L of heated water per day. From here, we get the new layout (see Appendix B), where the values are inputted in the MATLAB script overall_sys_eff_shortened.m. All other calculations are the same as in design 1.
Appendix B: Layout of islands
Design 1
Design 2
Appendix C: Cost analysis calculation
Calculation for cost per year to heat water for showering
References
- [1] Alibaba.com, “Copper tube 1/4 1/2 copper pipe for air conditioner and refrigeration,” Alibaba, 2026. [Online]. Available: https://www.alibaba.com/product-detail/Copper-Tube-1-4-1-2_1601719312246.html. Accessed: Apr. 5, 2026.
- [2] “Borosilicate 3.3 glass sheet (float glass),” Alibaba, [Online]. Available: https://www.alibaba.com/product-detail/Borosilicate-3-3-Glass-Sheet-Float_205628654.html
- [3] “High temperature resistant epoxy AB adhesive,” Alibaba, [Online]. Available: https://www.alibaba.com/product-detail/High-Temperature-Resistant-Epoxy-AB-Adhesive_1601665768447.html
- [4] “30-inch commercial restaurant stainless steel work table,” Alibaba, [Online]. Available: https://www.alibaba.com/product-detail/30-Inch-Commercial-Restaurant-Stainless-Steel_62513090513.html
- [5] “Free angle brackets for aluminum frames (LADU8-3030-S),” MISUMI, [Online]. Available: https://sg.misumi-ec.com/vona2/detail/110310155879/
- [6] “1/2–4 inch ASTM Schedule 40 pipe,” Alibaba, [Online]. Available: https://www.alibaba.com/product-detail/1-2-4-ASTM-Schedule-40_60514212108.html
- [7] “PVC water supply and drainage plastic pipe,” Alibaba, [Online]. Available: https://www.alibaba.com/product-detail/PVC-Water-Supply-and-Drainage-Plastic_1600262360998.html
- [8] “Chang En white/black inner-diameter … (product),” Alibaba, [Online]. Available: https://www.alibaba.com/product-detail/Chang-En-White-Black-Inner-Diameter_1601627726868.html
- [9] “Plate sheet 1–2 mm metal plate,” Alibaba, [Online]. Available: https://www.alibaba.com/product-detail/Plate-Sheet-1-2mm-Metal-Plate_1601650358104.html
- [10] “Factory wholesale SUS201 grey stainless steel,” Alibaba, [Online]. Available: https://www.alibaba.com/product-detail/Factory-Wholesale-Sus201-Grey-Stainless-Steel_1600995175835.html
- [11] “Type Of Water Pipe | High-Quality Plumbing Services Singapore,” Active-Plumbing. https://activeplumbing.sg/type-of-water-pipe/
- [12] “Stainless Steel Round Pipe Singapore | HiMetal,” HiMetal Enterprise Pte Ltd, Jun. 10, 2025. https://www.himetal.com.sg/stainless-steel-round-pipe/
- [13] “SS Pipe Size Chart - Nandishwar Steel,” Nandishwarsteel.com, 2026. https://www.nandishwarsteel.com/stainless-steel-pipe-dimensions.html
- [14] SSContent, “What Pipe Size for House Plumbing? A Complete Guide,” Splash Plumbing, Feb. 28, 2025. https://www.splashplumbing.com/what-size-pipe-for-house-plumbing-a-guide-to-choosing-the-right-dimensions/
- [15] S. A. Kalogirou and G. A. Florides, “Solar Space Heating and Cooling Systems,” Comprehensive Renewable Energy, pp. 501–531, 2022, doi: https://doi.org/10.1016/b978-0-12-819727-1.00003-0.
- [16] https://mypdh.engineer/lessons/controls/
- [17] Zhejiang Hailiang Co., Ltd., “Hailiang Custom Fireproof Black Rubber Thermal Insulation Pipe,” Made-in-China.com. https://hailiang1.en.made-in-china.com/product/QZNaBgfYaJcW/China-Hailiang-Custom-Fireproof-Black-Rubber-Thermal-Insulation-Pipe.html?acc=5494762105-lxy&cpn=21714728580-&tgt=&net=x&dev=c-&gid=CjwKCAjwspPOBhB9EiwATFbi5LcM3xtO6p1yNPq527jXaa6mTHovafQ-oeqxcfyLIuN9QMxQ_--SJxoCaNsQAvD_BwE&kwd=&mtp=&loc=9062542-&gad_source=1&gad_campaignid=21721137545&gbraid=0AAAAA-M7K1iP3cuouqCv8a6A5c06mehHi&gclid=CjwKCAjwspPOBhB9EiwATFbi5LcM3xtO6p1yNPq527jXaa6mTHovafQ-oeqxcfyLIuN9QMxQ_--SJxoCaNsQAvD_BwE
- [18] “Stainless Steel Oval Pipe 304/316/316L/304L,” Made-in-China.com. https://tjstdco.en.made-in-china.com/product/gbhmfRzjJdYA/China-Stainless-Steel-Oval-Pipe-304-316-316L-304L-Stainless-Steel-Oval-Pipe.html?pv_id=1jkhr2l2o62&faw_id=1jkhr3bqr58f&bv_id=1jkhrd2didb8&pbv_id=1jkhr2kca750r
- [19] “Factory Wholesale Stainless Steel Pipe Fittings SS304 SS316 Coupling,” Made-in-China.com. https://sxbhms.en.made-in-china.com/product/qwOGnyjdQXtl/China-Factory-Wholesale-Stainless-Steel-Pipe-Fittings-SS304-SS316-Coupling.html?acc=5494762105-lxy&cpn=23486536000-&tgt=&net=x&dev=c-&gid=Cj0KCQjw7IjOBhDyARIsAFzrWQyqeF31-hLCxTxBb_QmwmjvD6HwPgnEMRfilcqhx8pUtIkLYmGqc2UaAvZfEALw_wcB&kwd=&mtp=&loc=9062542-&gad_source=1&gad_campaignid=23481894866&gclid=Cj0KCQjw7IjOBhDyARIsAFzrWQyqeF31-hLCxTxBb_QmwmjvD6HwPgnEMRfilcqhx8pUtIkLYmGqc2UaAvZfEALw_wcB
- [20] Jiangsu Daocheng Stainless Steel Pipe Co., Ltd., “304 Thin Wall Stainless Steel Round Tube DN25 Home Water Sanitary Piping 316 Food Grade Stainless Steel Pipe,” Made-in-China.com. https://dcstainless.en.made-in-china.com/product/xElUaOgoaShi/China-304-Thin-Wall-Stainless-Steel-Round-Tube-DN25-Home-Water-Sanitary-Piping-316-Food-Grade-Stainless-Steel-Pipe.html?pv_id=1jkmiibvqdb8&faw_id=1jkmiifto5aa&bv_id=1jkmijpbu919&pbv_id=1jkmiibogb9bi
- [21] Bmag Brass Safety Air Pressure Relief Valve for Solar Water Heaters System, Made-in-China.com. https://bw-valves.en.made-in-china.com/product/yAZrsvNjceVk/China-Bmag-Brass-Safety-Air-Pressure-Relief-Valve-for-Solar-Water-Heaters-System.html?header_search_page=lv&pv_id=1jkhn9ggja55&faw_id=1jkhna2fqdfd&bv_id=1jkhna2fr23a&pbv_id=1jkhn9g0ncf4u
- [22] “24VDC 60W 80M 5L/min 0.8Mpa Low Noise Solar Diaphragm Water Pump,” Flowatt, 2025. https://flowatts.com/products/24vdc-60w-80m-5l-min-0-8mpa-low-noise-solar-diaphragm-water-pump?srsltid=AfmBOooZPgMUydhrP4uNn7OHztiEB3ZfKX77OlConWbjvBwdzXPRIrZ5
- [23] “200 psi 3/4 Inch Female Non-Return Valve Model Type H14W,” Made-in-China.com, Industry Valves. https://industryvalves.en.made-in-china.com/product/uqGntNkJOZAW/China-200psi-3-4-Inch-Female-Non-Return-Valve-Model-type-H14W-.html?acc=5494762105-lxy&cpn=21714728580-&tgt=&net=x&dev=c-&gid=Cj0KCQjw7IjOBhDyARIsAFzrWQz13uhEpRHQI5YCSV3M_pIuUDGNTyuBsTAPrx08GnNgzVEyHShcfgsaAsaGEALw_wcB&kwd=&mtp=&loc=9062542-&gad_source=1&gad_campaignid=21721137545&gclid=Cj0KCQjw7IjOBhDyARIsAFzrWQz13uhEpRHQI5YCSV3M_pIuUDGNTyuBsTAPrx08GnNgzVEyHShcfgsaAsaGEALw_wcB
- [24] “Grundfos Cr 255-6-2 Boosting Vertical Multi-Stage Centrifugal Water Pump,” Made-in-China.com, 2026. https://chinapumpsupplier.en.made-in-china.com/product/nmuRaAYxjyrw/China-Grundfos-Cr-255-6-2-Boosting-Vertical-Multi-Stage-Centrifugal-Water-Pump.html
- [25] “Aluminum Solar Panel Mounting Brackets with Adjustable Angle Design,” Made-in-China.com. https://vaaluminum.en.made-in-china.com/product/ERUrDWobVuhJ/China-Aluminum-Solar-Panel-Mounting-Brackets-with-Adjustable-Angle-Design.html?ads_tp=ppc&ads_id=CmrJWTlOanhK&ads_tp=ppc&ads_id=CmrJWTlOanhK&pv_id=1jlg8i38kb58&faw_id=1jlg8i9hv620&bv_id=1jlg8i9i00e
- [26] davidnoorma1, “Detail Tarif Listrik Berdasarkan Golongan Daya dan Jenisnya - PT PLN (Persero),” PT PLN (Persero), Dec. 12, 2025. https://web.pln.co.id/media/2025/12/tarif-listrik
- [27] A. M. Tegar, “Indonesia to boost renewable energy investment to shield economy,” Antara News, Apr. 2026. https://en.antaranews.com/news/410641/indonesia-to-boost-renewable-energy-investment-to-shield-economy
- [28] L. Julianti and A. K. Jaelani, “The Regulation of Renewable Energy in Indonesia Creating Green Investment for Tourism Industry,” Advances in Social Science, Education and Humanities Research, pp. 660–667, 2024, doi: https://doi.org/10.2991/978-2-38476-315-3_90. https://www.atlantis-press.com/proceedings/icpsd-24/126006814
- [29] "INFOGRAPHIC REPORT INDONESIA’S TOURISM DECARBONIZATION ROADMAP," wisestepsconsulting.id, 2023. https://wisestepsconsulting.id/wp-content/uploads/2023/10/Indonesias-Tourism-Decarbonization-Roadmap.pdf
- [30] Green Building In Indonesia: Criteria Certifications and Applicable Incentives – Nusantara Legal Partnership,” Nusantaralegal.com, 2022. https://nusantaralegal.com/green-building-in-indonesia-criteria-certifications-and-applicable-incentives/
- [31] "ASEAN Green Hotel Standard" Asean.org, 2024. https://asean.org/book/asean-green-hotel-standard-2/